CIL And Railways Advised To Prioritize Fuel Supply To Pithead Plants

0

(ET)

The government has asked Coal India Limited and the railways to prioritize fuel supply to pithead power plants irrespective of their quota or contracted quantity to help them run at full capacity and meet peak demand. CIL normally supplies a maximum of 90% of the requirement for running a plant at 85% capacity. In peak season, higher demand for coal congests the railways, making it easier to stock up pithead plants.
Not all coalfields have enough production to meet the demand of a pithead plant while some mines also cater to other customers.

Seventeen plants are located near coal mines. They have a total capacity of 33.18 GW comprising 21% of the total thermal capacity. In April-May this year, 13 out of them ran at 82-100% capacity. Their fuel stocks are sufficient for 12 days on average.